Firelands Local School district is building a new 106,643 square foot high school that will house 439 students plus supporting faculty and staff. The facility will be built in accordance with the Ohio Design Manual.
PREQUALIFICATION OF SUBCONTRACTORS GCS will be prequalifying subcontractors with criteria that has been pre-approved by the OFCC and the FLSD in accordance with the guidelines set forth by the State of Ohio for CMR contracting. More information and documents related to this project delivery format can be found at http://ofcc.ohio.gov. Although GCS will share information on bids received with the Owner, this is not a public bid opening. More information on bid delivery will be issued with the bid packages to pre-qualified subcontractors. Questions on the process should be sent to [email protected] Contractors wishing to be considered for pre-qualification must do so by providing information on the web-tool at the link on this page. Information will be treated as confidential, and only shared with the members of GCS and FLSD involved with the pre-qualification process.
SUBCONTRACTOR BID PACKAGES GCS will be receiving bids from prequalified subcontractors on the bid packages listed below. It is also GCS’s intent to allow for the bidding of Combination Bids. We believe that this practice will allow for additional competition in the market, sustain the viability of local general contractors and allow the inclusion of smaller subcontractors who might otherwise be ineligible. Scope indicated below are for general information, only. Detailed scopes of work will be issued with each bid package.
04A - Masonry
05B - Miscellaneous Steel Specialties
06A - Carpentry & Specialties
07A - TPO Roofing
07B - Metal Siding
08A - Glass and Glazing
09A - Metal Framing, Gypsum Board & Ceilings
09B - Resilient Flooring and Carpet
09C - Ceramic/Porcelain Tile
09D - Wood Flooring
09E - Resinous Flooring
09F – Painting
10A – Lockers
11A - Food Service Equipment
12A – Casework
21A - Fire Protection
22A – Plumbing
23A - HVAC & Integrated Automation
26B - Building Electrical
28A - Building Technology & Security
32B - Asphalt Paving Turning Lane
32C - Final Site Development
46A - Wastewater Treatment
Owner: Firelands LocalSchool District Location: Oberlin, Ohio Delivery Method: CM at Risk Architect: BSHM Architects Value: $23 million Size: 106,643sf
Early Site Bid Date: August 6, 2020
Early Site Construction Start: August 24, 2020
Structural Steel and Foundation Bid Date: December 16, 2020
Structural Steel and Foundation Construction Start: January 4, 2021
Building Packages Bid Date: January 29, 2021
Building Packages Construction Start: February 22, 2021